After the Warner Draw Debris Basin did not meet NRCS and Utah State Dam regulations, plans were made to update the dam to meet the correct standards. The project consisted of rehabilitation of six debris basins within the Warner Draw Watershed. Rehabilitation of these debris basins reduced the risk of flood damages in the area. JDE’s technical review included the design report, specifications, drawings, supporting calculations, cost estimate, geologic and geotechnical analysis, hydraulic and hydrologic design data, quality assurance plan, and operation and maintenance plan.